Mainly due to the weather and other jobs getting in the way, I have not done as much on the RR as I would have liked. Not pictured here but the wing and light box for the near side are both repaired, painted and ready to go back on. The drivers side still needs work as there was much more corrosion.
Progress with pictures. After earlier deciding I would try just to repair the rust damage leaving the floor in place, there was so much grot the more I trimmed the more I found so I got annoyed and just ripped the whole thing out.
- boot floor out.jpg (194.89 KiB) Viewed 1997 times
Just as well I did as underneath some chassis issues were revealed (both sides are the same so I will only post images of one)
- chassis rot.jpg (183.14 KiB) Viewed 1997 times
To get at this I had to take part of the rear floor out. Just as well I did as this is rotten too (not pictured)
but it allowed me good access to attack and re-create a rather important bit normally hidden.
- chassis cut out.jpg (185.8 KiB) Viewed 1997 times
- chassis patch 1.jpg (142.07 KiB) Viewed 1997 times
- chassis patch 2.jpg (181.45 KiB) Viewed 1997 times
Not the tidiest job in the world but given the silly angles I have had to work at, I don't think it's too bad. it passed the "whack it with a hammer and see if it falls off" test
I haven't got as far as completely repairing the drivers side but the top of the chassis itself is now solid.
I have also started wire brushing and k-rusting the original chassis as you can see in the pictures it is a bit flaky but bashing it with a hammer shows it to be solid.
Parts made / collected:
new boot floor and extension to replace the patchwork of metal that was there
lower rear tailgate seal mount
z sections to replace the corroded lip that the boot floor sits on
rear seatbelt bushes and mountings
all new brake flexi-pipes (the rear ones have unions made entirely of rust)
lots of grommets, P clips and cable clips.
Lots of 1.2, 3 and 5mm steel.
Still to get:
New LPG plumbing and a vertical 720x250 tank (if I can find one) with 2 smaller tanks under the rear quarters.
Next jobs:
Finish an identical repair on the other side of the chassis
brush off, rust treat and paint as much of the chassis as I can while I have good access to the top
weld in new mountings then re-fit the rear and boot floors
repair the drivers side rear wing and light box then re-fit
sort out the joke of an LPG system and re-fit the pipework more securely than a couple of screws and p-clips in to the sills.
All hopefully before winter :S